New Home Update – October 5, 2016
By the end of the day, Wednesday, Oct. 5, when the last
truckloads of fill are dumped, graded and compacted, site preparation will be
complete. As reported last week, the process began with the removal of tree
stumps, vegetation, the swimming pool, and poor quality fill that would not
support our structure.
New Home Update – September 28, 2016
In other news, the New
Home construction team, TEDCO and RDC discussed the issue of heating the
building over the winter. TEDCO has agreed to look into some options, which we
will discuss at a special meeting, and we expect to have a solution before the
heating season begins.
Also, a three-minute time-lapse video of the demolition
of the north wing has been published on YouTube. It can be accessed at: https://www.youtube.com/watch?v=T-ECiJgTeDI
.
New Home Update –
September 21, 2016


New Home Update – September 15, 2016 (From the October Drummer)

Earlier in the month a new team was formed to oversee the
construction of the building. The team meets every other Tuesday with our
contractor, TEDCO, and our architect, Rothschild Doyno Collaborative (RDC), to
review progress of the building, approve changes in scope, and authorize payment for work done. The team is also responsible for communicating with the
congregation. At its most recent meeting the team reviewed the design changes
mandated by Mt. Lebanon to meet its fire code, which is much more restrictive
than the state code. The most significant change was to create separate “fire
areas” of less than 5,000 square feet to eliminate the need for sprinklers,
which are prohibitively expensive. RDC’s design solution will turn the rear
wall of the sanctuary into a fire barrier by adding a second layer of drywall
and installing fire resistant doors. In addition, the new plans call for fire dampers
in certain air ducts, additional smoke detectors and emergency lighting.
At the same meeting Denny McCracken reported that we had
received the final documents for our construction loan from Huntington Bank.
The agreements have been signed by President Denny McCracken, Vice President
Jay Thornton, and Treasurer Regina Yankie. Our loan is now secured, and all of our
financing is in place.
Now that the church is a full-blown construction site, TEDCO
has installed fencing along the front and sides of the property and lockable
gates on the driveways from Washington Road and Sunnyhill Drive. These gates
will be locked at night during the work week and all day Saturdays and Sundays.
Our access is from Sunnyhill Drive. That gate has two padlocks linked together
– one belongs to Sunnyhill and one is owned by TEDCO. Anyone needing access to
the building in the evenings and on the weekends should see Roy for a key to
our padlock and a tutorial on how the locking system works. The gate is heavy
and not easy to open, so be careful.
Finally, with cold weather approaching an issue that we are
addressing is heating the portion of the building we are occupying. While the
offices, kitchen and bathroom must be heated to comfortable temperatures for
our staff, the fellowship hall only needs to be heated to about 45 degrees to
prevent the building from deteriorating due to the cold. TEDCO is working on a
solution, which should be in place before heating season begins.
The New Home Construction Team will continue to provide
updates in The Beat and The Drummer, and once demolition is
completed, we will post a time lapse video of the process on our website.
New Home Update – September 14, 2016
New Home Update – September
7, 2016
Although we submitted our plans for township approval on
July 26, we are still waiting for our building permit. While we can continue
demolition and site preparation without the permit, we cannot begin
construction until our plans have been approved. The approval process was
initially delayed while Mt. Lebanon hired a new building inspector. Then we were
told that our plans did not comply with Mt. Lebanon’s fire code. Our architect,
Rothschild Doyno Collaborative, has reworked the plans to address the issue,
and Mt. Lebanon has agreed in principle that the modifications are acceptable. A
meeting to finally resolve the issue is scheduled for Friday, and we expect to
have the permit in hand shortly thereafter.
New Home Update – August 31, 2016
Our months of planning, fundraising and due diligence are
finally going to bear fruit. On Tuesday, Sept. 6, TEDCO, our construction
manager, will begin the 10-month process of building our new home. During the
first week of the project, the infrastructure for the new construction will be
set up. Office trailers will be placed in the parking lot, construction site
boundaries will be established and signs designating construction and staff
entrances will be installed. At the same time crews will be working inside the
building to separate the utilities – electricity, gas and water – so the north
wing can safely be demolished while our staff continues to work on the premises. To secure the fellowship hall and the south
wing of Sunnyhill and protect them from the elements, temporary walls will be
built on the main floor and in the basement.
The second phase of the project, demolition of the north
wing will take place between Sept. 14 and 21. The third phase, site preparation,
will begin immediately after demolition. This phase will include removal of the
swimming pool, pulling out tree stumps and grading the site so footings can be
dug and construction can begin in earnest. Throughout the construction process
the New Home team will meet regularly with our architects and construction
manager to ensure that we stay within budget, on schedule and our design goals
are met. The team is also committed to communicating the progress of our
project with the congregation through articles and photographs in The Beat and The Drummer.
Beginning next week, if you have a meeting or business at
Sunnyhill, please use the entrance off Sunnyhill Drive and park in the row of
spaces in the southernmost part of the parking lot, which will be reserved
exclusively for our use. Construction sites can be dangerous, so please respect
the boundaries established by our contractors. If you must go into the
construction zone, check with the construction manager first and please wear a
hardhat, which will be available in the office.
No comments:
Post a Comment