Georgia buggies were used to move concrete from
the transit mixer to the west end of the sanctuary.
|
Concrete for the east end of the building was
poured directly from the transit mixer.
|
The laser in the left of this photo was used to
guide the power screed so the slab would
be perfectly level.
|
A power, laser guided screed in action.
|
Troweling was done using both a powered trowel
(foreground) and the old-fashioned way with
hand trowels (background).
|
Temporary bracing kept the wooden forms in place.
|
To prevent movement in the steel columns from
cracking the floor, the area around the base will
be filled with an isolation pad.
|
Craig Frye, our construction manager from TEDCO and his associate, Scott, had to remain on site until the concrete had hardened enough to be walked upon without leaving marks so they could cover it with insulated plastic tarps. These covers will help keep in the heat generated by concrete in the normal process of curing and keep the slab above 40 degrees Fahrenheit until it cures enough to be exposed to weather. Generally concrete reaches 70 percent of its strength in seven days and full strength in 28 days. Craig and Scott began covering the floor just after 8 p.m. and were nearly done by about 8:45 p.m. They expected to finish by 9 p.m.
Placing the slab required seven transit mixers, each hauling 10 cubic yards of concrete. To compensate for the temperatures, the concrete was made with hot water and a chemical accelerator was added to speed curing. This will result in additional costs, which will be absorbed by the contingency built into the budget. We had expected to be pouring concrete in the late summer, but the start date of our project was delayed three months for a variety of reasons.
Tomorrow, Thursday, CTS will return to pour isolation pads around the columns, place the slab in the basement - which will take eight to nine yards of concrete - and to cut expansion joints in the concrete poured today.
Tomorrow, Thursday, CTS will return to pour isolation pads around the columns, place the slab in the basement - which will take eight to nine yards of concrete - and to cut expansion joints in the concrete poured today.
Placing the slab isn't the only exciting news coming from the work site. For the past week, carpenters have been busy - even on the coldest days - framing and erecting the exterior walls of our new home. If you can read the language of wall framing - studs, king studs, jack studs, cripples, headers and sills - you should be able to see where the doors and windows will be installed. Once the floor is finished and the holidays have passed, framing our new home will take center stage, and we should see rapid progress. The goal is to get the building "dry" as quickly as possible. Look for an update on framing in next week's blog.
In other news, look for a link to the steel erection video in the right column of this blog. The most dramatic changes took place on day one, but if you look closely on day three, you can see the bright light from welding strategic joints taking place.
A view of the slab through a window in a new RE room and an
exterior door on the north side of the building.
|
Scott, left, and Craig from TEDCO putting the slab to bed
for the night.
|
Carpenters continued to fabricate wall sections even as the
slab was being placed.
|
The steel frame has been welded at strategic locations.
|
No comments:
Post a Comment