Wednesday, April 5, 2017


The painting section of the blog was updated on April 6, 2017, with the latest information following a chat with the painter.


Originally scheduled for Monday or Tuesday of this week, digging the trench for gas, water and conduit has been postponed until Monday, April 17. 

One morning prior to April 17, a crew will arrive with a large concrete saw to cut through the asphalt in our parking lot to prepare the site for trenching. Cutting the pavement will not affect operations at the church: the crew will be there and gone before we are up, says the contractor. RYCO will dig two adjoining trenches. 

The north side of the trench for the water line will be 4-feet to keep it below the frost line. Since it’s not affected by frost, the south side of the trench for the gas line only needs to be 2-feet deep. In these photos, you can see the path the trench will take across our property to connect to the utilities at the curb.











One of the more challenging aspects of adding a new wing to an old building is making them fit together. While the new sanctuary, offices and classrooms will have hybrid heat-pump forced air heating and cooling, our historical building will still rely on circulating hot water heat. To heat the historical building, pipes are being run from the boiler in the mechanical room of the new building under the stairway into the old building where they will connect with the existing pipes that feed our radiators. Circulating hot water is a loop system. Water flows through the radiator and returns to the boiler to be reheated. Because we will have two heating zones in the historical building, four pipes are needed, two to feed the radiators and two to bring the water back to the boiler. Hangers for the four pipes can be seen in the "purple wall" photos. The holes in the wall go through into the mechanical room where the boiler and the pumps for the two circuits (zones) will be. One zone will be the fellowship hall; the other zone will include the front foyer, dining room, kitchen and old attic.



The cover was removed from one of the chases in the basement ceiling to allow new pipes to be connected to the old pipes that feed the radiators in the fellowship hall above. Vents in the chases allow heat from the pipes to warm the basement room. This is the only connection where threaded couplings will be used. All other pipe connections will be welded using an arc (stick) welder. In this photo an el (elbow) has been welded to a section of 2.5 inch black iron pipe, which is the standard pipe for circulating hot water heat.


The hot water pipes for the old fellowship hall originally ran through the two holes in the right side of this photo. This wall will be repaired and will frame the entrance for the large basement classroom.












Steps to the basement have been installed, making it much easier for workers to get to and from the basement where a lot of work is currently underway. When completed, the steps will have wooden treads and risers and a wooden banister. When the north wing was demolished, TEDCO saved the tops of the newel posts; they will be reinstalled on the newel posts of the new stairway. Squeezing past other people going up and down stairs will be a thing of the past in our new home. The two panels seen on the right in the photo of the top of the stairs cover windows that will allow light from the large stairwell window to enter the main foyer of the building and people entering the church to look into the stairwell. It will be interesting to see what the art committee decides to put on the wall opposite those windows.









While on the subject of stairways, the next two photos are the side rails and the steps for the "ships ladder" that will provide access to the attic.The ladder will be very steep. The rails sit at a 75-degree angle, and the grate steps are 12 inches apart. 

 
Another sign of progress; the insulation has been removed from the temporary wall separating the old fellowship hall from the new addition. The wall will remain for now, but will be modified to allow finishers to patch the ceiling where our two structures come together.







In this photo looking east, a corner of the back wall of the old fellowship hall can be seen. The temporary wall is to the right. The large patch with the pointed top is where the entrance to the balcony used to be. The opening below is one of two rectangular arches into new building. At the very top of the photo is part of a patch where the exit to the patio used to be. It is now the second entry into the new building.


 Saving the best for last; while much construction remains to be done, certain areas are getting finished. The newly rebuilt front doorway has been stained to match our existing dark oak color. It awaits our new front door, which will have large glass panels, open out, swing to the left and have an ADA approved automated opener. We saved the hardware from the old door and will use the door handle as a pull on the new door.
The north exterior of the new sanctuary has its final coat of stucco. The soffit under the eve still needs to be painted to match the doors and windows, but otherwise, this is how the outside of the building will look. 






This interesting photo of the north end shows the stucco in three stages from left to right: 2-inch rigid foam (white with dimples); the grey base coat and the white final finish. The brick work under the windows has also been completed. The plywood door, which is the primary access to the site for the trades, will be among the last things replaced. The door will feature a side window that will allow light into the north end of the hallway. An exposed aggregate pad and sidewalk to the parking lot will make this entrance ADA accessible.



Moving inside the church, the rear (east) wall of the sanctuary has a coat of tinted primer. While the color is similar to the color we chose for the wall, it is not the true color. The wall will be sanded, and the final coat(s) will be applied.








The south wall of the sanctuary has also received a coat of tinted primer. The wheelchair ramp to the stage will have ADA approved railings on either side. Window sills will be added to the windows when all the finish carpentry is done. The steps to the stage will be hardwood. The remainder of the stage will be carpeted to match the floor of the sanctuary.





The two steel beams seen on the left in this photograph have received the first coat of paint. In this case, the color is correct. The paint is Sherwin-Williams DTM (direct to metal) paint, which is specifically formulated for painting steel and other metals.





Thursday, March 30, 2017

On Monday or Tuesday, weather permitting, a trench will be excavated across Sunnyhill's front lawn and parking lot to install new, larger gas (3-inch) and water (2-inch) lines to meet the greater demands of our new restrooms and heating. The trench will cross the front lawn and enter the building at the approximate locations shown in the photos. If you come to Sunnyhill next week, please plan to park on Sunnyhill Drive so our lot is clear for the excavation. Because the trenches will cross the temporary entrance to Sunnyhill, until it is back filled, and we have the all-clear from TEDCO, please enter through the kitchen. Roy will have the door propped open. As always, please use extreme caution in the construction zone.

The gas and water line will share, sort-of, the same trench. Each line has different requirements. Water lines must be buried below the frost line, which is 36 inches in our area. The gas line does not need to go below the frost line, and will occupy a shallower section of the trench at a specified distance from the water line. While the trench is open, our electrician will install two large conduits with pull-cords inside them. The conduits will be 1 1/2" or larger in diameter, will enter the building near the gas meter, cross the parking lot and be "stubbed up" just beyond the hedge, but not in the lawn where they will impede mowing. These conduits will one day be used to provide electricity to an electronic sign or for lighting for our existing signs.

As announced in the Beat, the New Home team, with the counsel of our architect, Ken Doyno, selected the carpet and the paint for the new addition and the sections of the historical building that are being renovated. In addition to carpeting the offices, classrooms, hallways and sanctuary, we will have new carpeting in the old fellowship hall and the large basement classroom. We also plan to purchase the same carpeting for the room formerly known and the fish tank/rainbow room and the hallway to the exit door.



Paint samples left to right are:
Dark –Morris Room Grey SW 0037
Middle – Sandbar SW 7547

Light – Panda White SW6147
To better see the colors, click the link to the Sherwin Williams site.


RDC has provided a floorplan showing which walls get which colors. We've also asked TEDCO for a quote to patch and paint the ceiling in the old fellowship hall and the walls. 






In other news, our crew is moving rapidly in applying the stucco to the exterior of the building. In these photos you can see that the two base layers have been applied and all that remains is for the finish layer to be troweled on to match the texture of our existing stucco.















Bricklayers have almost finished applying the brick veneer under the windows.













The new door to the rear of the old fellowship hall has been installed, which means that all windows and exterior doors are in place.











In the interior, the basement is being framed in and drywalled. This photo is the bottom of the stairwell. Conduit is in place, but the new gas and water lines have yet to be installed. Once done, carpenters will frame and install our new steps to the basement.








Pumps for hot water (for heating) wait to be installed. The large tank is an expansion tank, which is also part of our new hot water heating system. The box in the lower right of the photo contains our new high-efficiency boiler that will heat the water for the radiators in the historical section of Sunnyhill and provide additional heat, if needed, for our new HVAC system for the sanctuary.





Thursday, March 23, 2017

This blog post was revised March 24, 2017, to correct an error relating to the thickness of the foam insulation under the stucco and replace the photo.


Insulating our new home is nearly complete. On Wednesday, a crew began blowing insulation into the space between joists that support the ceiling and attic floor above wing of the addition that houses our offices, RE rooms, choir room, crying room and restrooms --for ease of reference, the office wing.


The two most common types of blown-in insulation are cellulose, made mostly from recycled newspapers with a fire retardant, and fiberglass. For our purposes fiberglass was the only choice because it is the only way we can achieve the R-38 insulation value specified in the design. 

Blowing insulation into an enclosed space is a labor intensive process. Our crew from Mincin Insulation Service consisted of two men. One was assigned to drilling holes between the joists in our new ceiling and the other was tasked with blowing in the insulation. They used Owens-Corning AtticCat expanding fiberglass. The insulation is run through a machine, seen on the left in the picture of the truck, that according to Owens-Corning, "conditions the insulation by breaking it up and fluffing it, [and] adding millions of the tiny air pockets that give the material its insulating power."


The insulation is further conditioned as it travels through the hose. As the picture shows the hose has two components - a corrugated section like a vacuum cleaner hose and a smooth section. The smooth section is pushed through the holes in the ceiling and backed out as the void fills with insulation. Once the void is full, the installer puts a plug into it. When the insulation crew is done, drywall finishers will return and patch all the holes. Once the ceiling is painted no one will ever know the holes were there. 




This photo shows what the expanded AtticCat fiberglass looks like. The installers were, surprisingly, not wearing dust masks. When asked why, they reported that the blown-in fiberglass does not create dust like cellulose, and it is not itchy like the fiberglass used in batts.


Once the blown in insulation is finished, the only insulation remaining to be completed is the 2-inch rigid foam insulation, seen in the photo, which goes on the exterior of the building under the stucco. 

To recap the different types of insulation in our building: the roof over the sanctuary is insulated with 4-inch thick rigid foam between the wood decking that forms the ceiling and the sheathing that is the substrate for the shingles on the pitched roof and the rolled rubber on the flat roof. All of our exterior walls are insulated with 5 1/2 inches of mineral wool. The cathedral ceiling of the RE-Choir room is insulated with R-38 fiberglass batts. The roof and suspended ceiling of the attic are insulated with R-30 fiberglass batts. And, now the ceiling of the office wing is insulated with R-38 blown-in fiberglass. 


While it's not an exterior wall, the rear wall of the sanctuary is insulated with 5 1/2 inches of mineral wool for its fire retardant qualities, and the walls of the restrooms have been insulated with fiberglass batts for sound attenuation.










The commentary on insulation would not be complete without a mention of the attic space, which has been nicknamed the Taj Mah-attic. The attic is not heated or cooled, but because it houses air handling equipment and water lines, it has to be "tempered space." Tempered space requires insulation, just not as much as our occupied, heated and cooled space, called "conditioned space." To best meet the need, the walls and portions of the roof of the attic were insulated and drywalled and a drop ceiling was added with fiberglass batts on top. It has become, as you can see in the photo, a rather nice looking place, which most people will never, ever see. When the HVAC is completely installed, the blog will include a photo of the maze of ducts criss-crossing the floor and going up through the ceiling, and then we will turn off the lights.




Other essential parts of our heating and cooling system will be installed in the new-ish utility room in the basement. New-ish applies because the concrete block wall in the top of the photo is a new wall, but the parged wall on the left is a historical wall that has been patched and repaired. The old basement floor has also been replaced. When Sunnyhill was originally built, it was common for concrete basement floors to be only about 2 inches thick. The new 4-inch thick floor is more substantial. In addition, concrete pads have been added to support the furnace, pumps and other heavy equipment that will occupy this space.


On the subject of infrastructure, this circuit-breaker panel is located in a storage room across from Roy's office. It is the primary circuit-breaker box for the new addition and contains 42, 20-amp circuits. For the uninitiated, the white wires are neutral, the red and black wires carry the current and the green wires are ground wires, which are designed to prevent shocks. A similar panel for the historical section of the building will be installed in the basement in the area designated as the new RE library, but which for years served as an office for Mushroom.


The five sections of conduit seen in this photo will run under the steps and the landing of our new stair case. Joining them will be two pipes that will carry hot water from our new boiler to the radiators in the historical portion of Sunnyill and back to the boiler; our system is circulating hot water. A gas line and a water line will also run under the steps. On the other side of the purple and white wall at the top of the photo is the utility room. The new stairway will incorporate newel post caps rescued from the original Sunnyhill stairway before it was demolished.

This niche in Jen's office is the above the open coat closet in the hallway. A similar niche is in Rev. Jim's office.

This is one of two open coat closets -- no doors -- that will be on the east wall of the hallway in the office wing of the building.











The right side of this photo shows the wall that will hold the sculpture recognizing those who financially supported the building of our new home. On the far left, temporarily covered with Tyvek, is the window to the infant-toddler room. In between is one of two entrances to the sanctuary.
 Looking out from the door to the sanctuary next to the infant-toddler room the two large openings leading to the old fellowship hall can be seen. On the far left is where the rarely used door from the rear of the fellowship hall to the steps was located. When finances permit, a television monitor that will display church announcements will be mounted on the other side of the wall in between the openings.



The area under the window of Roy's office is being prepared for the brick veneer that will be a feature under all of the windows on the front of the building. The brick veneer will tie the design of the façade of the new building with that of the old.








In other news, the New Home Construction Team met to pick carpet for the church. We will be carpeting the sanctuary, all of the offices and classrooms, the hallway and the various entry ways, the old fellowship hall and the large RE room in the basement -- so it's a lot of carpet. From an array of choices, we picked four that are available in our time frame and made a tentative decision. Since carpet will be a major design element of the new church, we are meeting with our architect on Tuesday to review our choice and make a final decision. We are using carpet tile, which will allow us to replace sections of the floor with wine and coffee stains that cannot be removed. At that same meeting, we will also select paint for the walls and the steel structure. An indication of how far along we are is that paint choice is now on the critical path. The sanctuary looks like it's just about ready for primer. The other rooms are still a few days away. We also selected the tile for the restrooms. The floor will be a 12X12 tile with the appearance of stone -- since it's impossible to describe, look for a photo as soon as one is available -- and the wall tile will be white subway tile as a nod to the original tile used when Sunnyhill was built.

Thursday, March 16, 2017

Approaching our new addition on Wednesday morning there was so much drywall going up that the electric drill drivers sounded like a swarm of bees -- zzzzzzit, zzzzzzit, zzzzzzit. And, indeed, the interior was a swarm of activity. Except for one small section adjacent to the infant/toddler room, the sanctuary has been drywalled, and much of it has at least the first coat of drywall joint compound. (This blog will use drywall as a noun and a verb.) This morning, Thursday, a drywall finisher was at work on the rear wall of the sanctuary applying another coat. The speed and skill these finishers demonstrate is fascinating to watch and impossible to describe with words. In fact, drywall finishing is such an art, that they have their own union called...the drywall finishers union. Tales are told of some finishers who are so good that no sanding is required. 


Entering the building reveals how tightly sealed it is. On the exterior, in addition to the Tyvek building wrap, the new addition will have one-inch thick rigid foam and a covering of modern day stucco. Inside, the exterior wall cavities are stuffed with mineral wool and the ceilings have R-38 fiberglass insulation. The interior walls are also being insulated with fiberglass batts for sound attenuation. The windows are all thermopanes, and only a few of them open to let in outside air. The average home depends upon leaking windows and doors for fresh air infiltration.

The tightness of the building begs the question -- will we run out of oxygen during our first service together? The answer to that question came this morning after a climbing a ladder into the attic where the HVAC is being installed to talk to Ron, one of our HVAC technicians. When asked about where the fresh air would come from, Ron pointed up to the two giant vertical ducts running through the ceiling and the roof. One of those, he said, will bring fresh, outside air into the air handler where it will be heated or cooled and blown into the sanctuary, the crying room, the restrooms and the hallway, which are all part of one heating/cooling zone. The offices, classrooms, choir room and infant/toddler room will all depend upon the passage of fresh air through the doorways during the normal course of the day. These rooms also have some windows that open.


The three offices, the RE room, the RE/Choir room and the infant/toddler room will each have dedicated HVAC units mounted in the eaves of the attic and controlled by thermostats in each room. The sealed building envelope and the HVAC plan are all designed to reduce our demand for energy, and thus our carbon footprint, and to save us money. What could be better way to celebrate St. Patrick's Day than being green and saving green. In this photo of the wall of the RE/Choir room, the electrical box on the left will house the thermostat and the electrical box on the right will accommodate the light switch. The location, so far to the left, is so they clear the door when it is open. Note that the boxes are perfectly aligned. The devil is in the details.


The RE/Choir room has other special features. For sound attenuation, the drywall on the walls between the room and the adjoining offices is mounted on resilient channel designed specifically for the purpose. These channels are mounted horizontally and at intervals of approximately two feet. 







The RE/Choir room also has an additional layer of rigid foam over the batt insulation in the attic.
The ceiling has R-38 fiberglass insulation. As mentioned in an earlier post, the rafters had to be deepened to accommodate that much insulation. As a side note, from the exterior, light coming through the triangular window that will be at the top of the room creates a very dramatic effect when viewing the building from the outside at night. It's like a beacon for religious liberals.




Purple drywall, which resists moisture, mold and mildew has been installed in the men's room...













...the women's room...













The janitor's closet, and the gender neutral restroom (not pictured).













 
Roy's office...







 The northeast corner RE room...
...and a storage room have all been drywalled. The protrusion in the corner is a chase for the HVAC duct that goes from the attic air handler, through the storage room and under the floor for heating and cooling the right half of the sanctuary. There is another chase in a closet down the hall. Who gets dibs on this storage?












This wall, with the exposed pipes and wires will be the first thing you see when you enter our new space from the old fellowship hall, and is the perfect place for donor recognition. Sculptor and woodworker Scott Smith is working on a dramatic design for the space that will recognize everyone who has contributed financially to building our new addition.





To wrap things up, this photo was not included to show the Tyvek, but to show the soffit of the small gable over the north hallway exit door.
The soffit for the northside of the building, seen here in white, is Azek beadboard, a plastic building material known for its durability. The soffit will be painted a grayish-tan to match the aluminum fascia (pebble stone) and the Pella window frames (clay).